Aquila: Arrived July 21st right on schedule. Demobilization is almost complete. Kale is having a couple of organizations over to review ways of improving communication bandwidth. As of the 25th will start constructing the sounding pole.

Joe Hunter says if there is interest in getting a copy of his DVD (The Search for the USS Grunion A Family Rediscovers its Past) email info@rememberproductions.com. He will monitor requests and if there are enough get it professionally burned. Price would just cover costs.

Schedules: ROV is scheduled to leave Cape Cod Friday 27th about 12:00. Should arrive at Seattle morning of the 31st.

Mobilization crew along with Pete Lowney should arrive at Seattle Monday July 30th

Mobilization should take 3 to 6 days. Then the trip to Adak, about 12 days.


1 Comment for 'Status Report July 25th'

  1.  
    Rick Lehtinen
    July 26, 2007 | 12:17 am
     

    Best of luck this summer. It is a wonderful project. I look forward to your posts.
    -Rick Lehtinen

Leave a comment

(required)

(required)


Information for comment users
Line and paragraph breaks are implemented automatically. Your e-mail address is never displayed. Please consider what you're posting.

Use the buttons below to customise your comment.


RSS feed for comments on this post | TrackBack URI